Roof Logistics Plan
Roof tear off building 3 is under way and scheduled for 8/13-8/25
Air conditioner stands will begin to be replaced Monday the 17th
They will begin the stand replacements from the south of the building (Unit 121/221) in the sections outlined in red and move to the north throughout the week. The air conditioning will be disconnected for a few hours when the air conditioner stand is being replaced. We apologize for any inconvenience or disruption this may cause, as we know many residents are working from home.