Roof Logistics Plan
Roof tear off building 6 is scheduled to begin 8/25
Air conditioner stands will begin to be replaced Tuesday the 25th.
They will begin the stand replacements from the North side of the building (Unit 155/256) in the sections outlined in red and move to the north throughout the week. The air conditioning will be disconnected for a few hours when the air conditioner stand is being replaced. We apologize for any inconvenience or disruption this may cause, as we know many residents are working from home.