Fence repairs have begun today. Below is the estimated repair schedule for the fences that were required to be partially removed. The installation of the new sections will be at a slower pace than when the fences were removed since the contractor is replacing those fence posts that were removed.
Building 7 (Units 157-169) July 31- August 5.
Building 1 (Units 101-111) August 3-August 9.
Building 3 (Units 121-127) August 7-August 12
Building 5 (Units 141-147) August 10-August 16.
Building 4 (Units 129-139) August 14-August 19